CAH-SVX01B-EN 67
Coil Piping and Connections
Dual-Circuit Condensing Unit: Evaporator Coil with Four Distributors
Figure 64. Dual-circuit evaporator coil with four distributors 1. Pitch the liquid line slightly—1 inch/10 feet
[1 cm/3 m]—so the refrigerant drains
toward the evaporator. See Figure 64.
2. Provide one expansion valve per
distributor.
3. Slightly pitch the outlet line from the
suction header toward the suction
riser—that is, 1 inch/10 feet [1 cm/3 m] in
the direction of flow. Use the tube diameter
that matches the suction-header
connection.
4. Arrange the suction line so the refrigerant
gas leaving the coil flows downward, past
the lowest suction-header outlet, before
turning upward. Use a double-elbow
configuration to isolate the thermal
expansion valve bulb from other suction
headers.
5. For horizontal tubing, use the tube diameter
recommended by the condensing unit
manufacturer.
6. For the vertical riser, use the tube diameter
recommended by the condensing unit
manufacturer. Ensure the top of the riser is
higher than the evaporator coil.
7. Pitch the suction line slightly—1 inch/
10 feet [1 cm/3 m]—so the refrigerant
drains toward the evaporator.
8. Insulate the suction line.
9. The top of the Circuit 1 suction riser must be
higher than the bottom evaporator coil. Use
the tube diameter recommended by the
condensing unit manufacturer for the riser.
10. The top of the Circuit 2 suction riser must be
higher than the top evaporator coil. Use the
tube diameter recommended by the
condensing unit manufacturer for the riser.